Introduction of Project

User introduction:

United Mymensingh Power Ltd. is a 200 MW (net) HFO fired Combined Cycle, Modular power plant in Jamalpur,Bangladesh. The power plant employs high efficiency, state-of-the-art engines and has introduced an environment friendly co-generation facility.

Feed water qualityThe water source is tube well water, and the feed water is high turbidity,high hardness, and silica. While the cooling tower required the ultra pure water, Based on the water analysis report, we designed pre-treatment (sand filter, activated carbon filter, softening)+ doule pass RO system+EDI system to make the output water quality meet requirement.
Capacity:6m³/hour output capacity (one work,one stand-by),recovery rate:75%
Output water quality:Conductivity of RO output water <5mg/l, Resistivity of EDI system<10Ω·m
Technical process:MMF+ACF+Softening+double pass reverse osmosis (RO) +EDI

Project Details

DATE:

Sep. 2018

CLIENT

UNITED MYMENSINGH POWER LIMITED IN BANGLADESH

CONTRACTOR

Xi’an Haohaijia (CHIWATEC) Water Treatment Technology Co.,Ltd.

Project Gallery

Water purifying machine for 200-MW power plant(1)
Water purifying machine for 200-MW power plant(2)
Water purifying machine for 200-MW power plant(3)
Water purifying machine for 200-MW power plant(4)
Water purifying machine for 200-MW power plant(5)
Water purifying machine for 200-MW power plant(7)

Do you have a water treatment project we can help with

Designing,machining,installing,commissioning, customize and one-stop service

    We will answer your email shortly!

    FOLLOW US